Description Commence Complete
Preliminary Design March 2016 January 2017
Final Design Permitting, Bidding Services February 2017 October 2018
Construction NTP to Substantial Completion November 2018 January 2020
Substantial to Final Completion February 2020 March 2020

The Phase 1 Project schedule extends over about 4-1/2 years. About 2-1/2 years will be involved with route selection, design, permitting, and land acquisition efforts. Construction is anticipated to begin in the Fall of 2018 and conclude in the Spring of 2020.

Back to main meeting page. Back to Phase 1 Interconnect Project main page.